Arc Flash

Arc Flash Accident Reports

An arc flash is dangerous and has the potential for causing serious injuries. It typically occurs suddenly and without warning - but not without a cause. Many arc flashes are caused by human error. The arc flash could have been avoided and the seriousness of arc flash injuries could have been reduced by those involved having followed proper procedures.

We'll take a look at the accident reports for five arc flash incidents to see if we can determine what happened; what should have been done differently; and how the accident could have been prevented.

The five arc flash accidents are:

Arc Flash  #1: On April 14, 2006, at the Brookhaven National Laboratory (BNL), an electrical engineer was injured by an arc flash while closing a fused-disconnect switch in an electrical panel.

Arc Flash  #2: On an oil drilling platform in the Gulf of Mexico, on November 20, 2009, an  electrician was investigating the cause for the loss of electrical power. While the electrician was inside the Motor Control Center (MCC) building, an arc flash occurred in a 480 volt breaker panel that resulted in first degree burns on the electrician's face and neck.

Arc Flash  #3: In Queensland, Australia on Thursday June 15, 2006 a Field Service Technician- Electrical, received severe burns when an 11000 volt arc flash explosion occurred inside a main incomer circuit breaker cubical.

Arc Flash  #4: On October 11, 2004 an electrician working at the Stanford Linear Accelerator Center (SLAC) received serious burn injuries requiring hospitalization due to an electrical arc flash that occurred during the installation of a circuit breaker in an energized 480-Volt (V) electrical panel.

Arc Flash  #5: On September 23, 2009, at the U.S. Department of Energy Savannah River Site, two electrical and instrumentation mechanics were troubleshooting a problem in a 480-volt circuit breaker cubicle when an arc flash occurred. One mechanic suffered second- and third-degree burns to his arms and face. The second mechanic was not injured because he had stepped away from the cabinet before the arc flash occurred.

Arc Flash Accident #1: Brookhaven National Laboratory (BNL)

An electrical engineer was injured by an arc flash while closing a fused-disconnect switch in an electrical panel. The electrical engineer, who was not wearing appropriate clothing nor the required PPE, received first and second-degree burns to his face and body.

The electrical engineer had been called in to help two electronic technicians troubleshoot a high-current ripple problem. Once the problem had been solved, they began restoring electrical power. The electrical engineer was closing four fused-disconnect switches on the 480-volt panel. When the third switch was closed he heard a very loud noise and saw sparks and smoke coming from within the panel.

The arc flash created radiant heat energy and molten aluminum, most of which was contained within the panel and was vented away from the electrical engineer. However, what was expelled from the front of the panel set his hair on fire and caused first-degree burns on his face, scalp, and chest. He also received first and second degree burns on his hands and forearms and a corneal abrasion to his left eye.

Arc Flash Investigation Results

Brookhaven Accident

The cause of the arc flash is believed to be an over-voltage condition resulting from a ground fault on an underground cable. This resulted in the initial arc between the grounded steel frame and the phase B bus. This arc resulted in phase-to-phase arcing within the switch.

The following are some of the conclusions in the accident report:

The accident report recommendations included:

Arc Flash Accident #2: Shenzi Tension Leg Platform in the Gulf of Mexico

An electrician was investigating the cause for the loss of electrical power to the Quarters building. While in the MCC building an arc flash occurred in a 480 volt breaker panel. The electrician received first degree burns on the left side of his face and neck. The fire alarm bell automatically activated when the MCC building sensors detected smoke, and a total platform shut-in was initiated with all personnel mustered to their designated duty stations.

Arc Flash Investigation Results

The arc flash incident investigation determined that a cable gland, mated to a Hub connector, was loose. This allowed rain and salt water spray to enter into the junction box. The water migrated by gravity feed approximately 185 feet through a conduit void from the power breakers to the Topside Control Center breaker enclosure.

The breaker internals showed evidence of water entrance and corrosion which suggests that small amounts of water entered the Quarters building power breaker over a long period of time. The water build-up inside the breaker broke down the insulation between phase A and phase B, and the arc flash was caused by a short between phase A and phase B.

There were no recommendations in the accident report.

Arc Flash Accident #3: In Queensland, Australia on Thursday June 15, 2006

A Field Service Technician- Electrical, working in a switch room, received severe burns when an 11,000 volt arc flash explosion occurred inside a main circuit breaker cubical.

Arc Flash Investigation Results

The investigation was not able to determine the cause of the arc flash. There was no evidence of:

It was noted that the safety shutters were not correctly labeled and there was the possibility of the failure of one shutter. In addition, the high voltage receptacles were not labeled.

Several factors contributed to the severity of the injury. Although the electrician had received the required training and a risk assessment had been carried out, the electrician was not wearing the correct PPE and had not followed required procedures.

The accident report recommendations included:

Arc Flash Accident #4: Stanford Linear Accelerator Center (SLAC) October 11, 2004

SLAC Accident

On the morning of October 11 an electrician was directed to install a new circuit breaker in an energized electrical circuit breaker panel. The supervisor had chosen the panel because it had an available slot for an additional circuit breaker.

At approximately 11:15 am, while the electrician was installing the new circuit breaker, an arc flash occurred igniting the electrician's clothing. The electrician received third degree burns on the face, chest, and legs and second degree burns on his arms. Approximately 50% of his body was burned. Because of the seriousness of his injuries, investigators were not able to interview the electrician.

Arc Flash Investigation Results

The results of an accident analysis concluded that arc flash was caused by the following:

The proper installation sequence for a breaker would have been to install the mechanical connections first. This would mechanically stabilize the breaker before making the electrical connections. The investigation revealed that none of the mechanical connections had been made, and phases B and C had been connected. The electrician was attempting to connect phase A but was having trouble with getting the screw to hold.

The investigation concluded that the electrician was using extra force to push on the screw in an attempt to get it to engage the threads on the bus link. This resulted in the phase A bus jumper bar deflecting toward the phase B stabilizing clip. The rubber insulation was compressed which increased the electric field stress in the insulation. The increase in electric field stress caused a failure of the insulation and resulted in an arc flash.

SLAC Accident Report

The following are some of the conclusions in the accident report:

Live parts to which an employee may be exposed shall be deenergized before the employee works on or near them, unless the employer can demonstrate that deenergizing introduces additional or increased hazards or is infeasible due to equipment design or operational limitations. - 29 CFR 1910.333(a)(1).

Employees working in areas where there are potential electrical hazards shall be provided with, and shall use, electrical protective equipment that is appropriate for the specific parts of the body to be protected and for the work to be performed. - 29 CFR 1910.335(a)(1)(i).

The accident report recommendations included:Stanford linear accelerator arc flash accident

Arc Flash Accident #5: September 23, 2009 at the DOE Savannah River Facility

Savannah River Arc Flash Accident

Two E&I Mechanics were troubleshooting a breaker that would not close. The breaker was located in an energized cabinet. A 9-inch torpedo type level was being used to level the track that was causing breaker misalignment. The level fell from the top of the chute down the left side of the breaker and is suspected of having lodged between the phase "A" breaker moving contact and the breaker support brace, resulting in an arc flash.

The arc flash severely damaged the left side of the breaker, splattered material in the cabinet and surrounding area, and embedded slag in electrical equipment ten feet away.

One of the E&I Mechanics, who was not wearing a flash suit nor flame-retardant coveralls, noticed the level fall and covered his head and face with his arms. He received second and third degree burns on his arms, and first and second degree burns on the right side of his face. The other E&I Mechanic had stepped away from the cabinet and was outside the effect of the arc flash.

Arc Flash Investigation Results

Based on the condition of the circuit breaker and cubicle, the investigation determined the fault current was interrupted before the short was able to develop a plasma arc cloud which would have made the event a fully engulfed arc flash and creating more extreme consequences and injuries.

The following are some of the conclusions in the accident report:

The accident report recommendations included:

Visual Communication Using Labels and Signs Helps Prevent Arc Flash Injuries

Several of the above reports identify not following procedures as contributing to the arc flash, or the severity of the arc flash injuries. NFPA 70E provides the minimum requires for arc flash warning labels. In addition to those required by NFPA 70E, signs and labels can be used to remind employees about required procedures and PPE. For example, a sign on doors into electrical rooms might say: "Ensure Require PPE I Being Used Before Entering."

Signs and labels made using DuraLabel printers and supplies provided needed warnings and information right at the location where it is needed. From NFPA 70E required labels, available in both standard and extra large sizes, to making signs that provide information about procedures, operating instructions and even first aid, DuraLabel is the leading printer brand used around the world.

Label printer literature

Try the free online Arc Flash Labeling Quiz

What Is Arc Flash? | Arc Flash Label Requirements | Arc Flash Label Printers
Links to Other Arc Flash Resources

Click here to request your free arc flash best-practices guide

follow this link for a free arc flash one page quick reference guide

follow this link to receive your free safety inspection guide

follow this link to receive your free safety inspection guide

Printers & Labeling

NFPA 70E and Arc Flash

Arc Flash Articles

Special Offers

 

Contact Request

Back

Call 1.888.326.9244 to speak with a safety labeling expert.